PBES Innovative Projects

Church Street Bridge

LocationNew Haven Interlocking and Rail Yard
StateCT
Completion Date2003
Contact PersonLarry D'Addio, P.E.,
Connecticut Department of Transportation
Description

This truss-span bridge is 1,280 ft. long with 8 spans including 320-ft. truss span, 50 ft. high and 60 ft. wide.

The Church Street South Extension project provided a new steel truss bridge over the New Haven Interlocking and Rail Yard, directly linking downtown New Haven and the Long Wharf and waterfront areas. To minimize disruption in the rail yard and improve work-zone safety for a crew working over active rail lines, ConnDot required that this portion of the bridge be completed in a single weekend night.

The 320-ft long, 850 ton prefabricated truss center span was constructed over several months next to the active rail lines and then lifted into place on an early Sunday morning in May 2003 by a single high-capacity crane owned by Lampson International LLC. The crane, which required more than four weeks to assemble, lifted the entire truss span more the 65 ft. and moved it more than 100 ft. to its final position. Specifying prefabrication saved ConnDOT about a year on its overall contract time and at least $1.1 million. Prefabrication of the center span greatly improved constructability for O&G Industries; the center span could not have been built during the limited working hours allowed by the rail yard. Using prefabrication on this project avoided closure of 4 tracks during bridge construction.

PhotoPrefabricated truss center span being lifted into place for Church Street South Extension in New Haven. Click for larger version of image.
Prefabricated ElementsTotal superstructure systems
Other Keywordstotal superstructure prefabrication
AdvantagesMinimized traffic disruption,
Related Document 1850 Ton bridge lifted into place by world's largest mobile crane
Photo CreditsConnecticut Department of Transportation

Events

More Information

Contact

Reggie Holt
Office of Bridge Technology
202-366-4596
E-mail Reggie

 
 
This page last modified on 05/12/08
 

FHWA
United States Department of Transportation - Federal Highway Administration